A detailed breakdown of an independent safety investigation into a fatal arc flash incident during the commissioning of a greenfield power plant. We examine the timeline, the human factors, and the mechanical and design failures behind the tragedy.


Chapter 1

Ten Minutes

Theo Ashworth

The last thing we know the engineer said was that he'd fix it in ten minutes. He said it over a radio, to a colleague standing at a pump, a little after midday. Ten days later he was dead. That's the case behind today's episode. It comes from a safety case written by Dr Wayne Sundborg, an independent investigation carried out with the help of a consulting expert engineer. Everything in it is anonymised, so we're working with roles rather than names. There's the Project Management Team, the EPC Contractor, the Subcontractor who employed the engineer, and the Equipment Supplier.

Nell Harding

And because this is a death, I think we should be plain about how we'll handle it. We'll stick to what the report establishes, and where the investigator says something is an inference, we'll say so too. Where is this, then? What kind of site are we on?

Theo Ashworth

A greenfield independent power plant. It's an integrated combined cycle gas turbine plant, so several gas turbines, steam turbines, heat recovery steam generators and cooling towers, fired mainly on natural gas with liquid fuel as backup. It's under commissioning, and commercial operation is expected shortly afterwards. The main EPC Contractor had handed the water treatment package to a specialist Subcontractor. That firm was responsible for the demineralisation plant, the Demin plant, including the electrical panels, the PLC and the drives. At the time of the incident the Demin plant was in the final stage of commissioning, and most of that Subcontractor's workforce had already been demobilised.

Nell Harding

So a thinned out crew, near the finish line. Hold on to that. Who's the engineer?

Theo Ashworth

A young man in his late twenties, an Electrical and Instrumentation Engineer employed by the Subcontractor. He had a bachelor's degree in technology and about four years of experience. The report is careful about his profile. His record was predominantly PLC and instrumentation systems, with no demonstrated hands on electrical systems competence. His training was a commissioning safety induction and permit receiver training. There's no evidence he'd been trained on the panel in question.

Nell Harding

I'd put that in everyday terms, if I may. It's someone who can tell you exactly why a controller is misbehaving, but who hasn't been shown how to work safely inside the heavy power equipment behind it. That's my interpretation, not the report's wording, but it seems to be the gap the report is pointing at.

Theo Ashworth

Yes, I think that's fair. Now the timeline. The day before, around nine in the morning, the Subcontractor obtained a general permit to work for commissioning of the motors, valid for several days. A no load trial run had been reported as completed successfully, using local push button operation. On the incident day, around five to twelve, the engineer and a colleague were assigned to carry out the load trial run of a feed pump stream. He signed the switchroom entry log, which was kept by a security guard at the door. Work began around twelve, during the EPC lunch break, with no EPC supervision present. He was at the switchgear and his colleague was at the pump.

Nell Harding

He starts the pump from the PLC, and it trips.

Theo Ashworth

The motor tripped after the initial run up. In the summary, it's described as failing to transition from star to delta during start up. For anyone who hasn't met it, star delta starting is a way of being gentle with a big motor. It starts in one winding arrangement to limit the surge of current, then switches over to the other once it's up to speed. So the pump started, and the changeover didn't happen. The report doesn't tell us why. What it does tell us is that post incident testing found the motor and its cable healthy, and we'll come back to that.

Nell Harding

And that's when he tells his colleague about the ten minutes.

Theo Ashworth

He radioed that he would rectify the fault in ten minutes. Then he went to the panel. He opened the cable alley, using a switchgear door key that the report says he held but wasn't authorised to hold. He removed the front plate of the instrumentation and control box, the I&C box, on the low voltage switchgear. The tool he used was a 240 volt test screwdriver, the maximum rated tool available to him.

Nell Harding

A 240 volt tester screwdriver, on a low voltage switchboard. I know we'll get to what that means, but I just want that detail to sit there for a second.

Theo Ashworth

It's the detail that stays with you. Now, here's the point where the report flags an inference. It's inferred that the detached metal cover plate was set down on a cabinet fixing bar to his right. It slipped, struck the cables below, and came to rest on exposed busbars. A phase to phase arc flash followed, and he was engulfed in flames. The security guard at the entrance put the flames out with carbon dioxide and dry powder extinguishers, and alerted his supervisor, who informed the EPC HSE coordinator. A site nurse gave first aid, and he was taken to a local government hospital.

Nell Harding

The investigator is open about the limits of the evidence there, isn't he?

Theo Ashworth

He is, and it matters. The witness statements were taken by the EPC HSE team rather than an independent party. By the time of the independent investigation, none of the witnesses remained available on the project. Documentary copies couldn't be re verified at source. And the precise way the cover plate reached the busbars is, in his words, an inference based on experience of similar events. So we have a firm physical outcome, and one step in the middle that's reasoned rather than witnessed.

Nell Harding

The injuries, then. I'd rather say them once and plainly.

Theo Ashworth

Burns to more than ninety per cent of his body surface. About sixty per cent was partial thickness, and more than thirty per cent was full thickness. There was also third degree burning of the airways, lung damage from inhaling flame, and acute trauma to the larynx, trachea and bronchi. The investigator says that pattern is consistent with direct engulfment in an arc flash fireball at close range, without arc rated protection. The inhalation burns show he was within the immediate plasma and flame envelope. And he states that appropriate arc flash PPE and an enforced minimum approach boundary would have materially altered the outcome. He died ten days after the injury.

Chapter 2

A Panel That Should Not Have Opened

Nell Harding

Let's start where an investigator has to start, which is whether something electrical went wrong first. A pump fails to change over, an engineer goes to look. It would be easy to assume the equipment failed and the fireball followed.

Theo Ashworth

The report closes that door. After the incident, the motor and its connecting cable were tested. There was no phase to ground fault, and both were found healthy. On the facts collected, no electrical fault was present that would have caused the arc flash. On the engineering assessment, an electrical fault is a highly unlikely cause. The initiating mechanism was mechanical. A metal plate touched live busbars.

Nell Harding

Which is almost banal. A plate slides off a bar. It's the kind of thing that happens in any workshop, a panel or a lid set down where it shouldn't be. The question must be why that ordinary slip could be fatal.

Theo Ashworth

Right, and the answer is in the build of the panel. This is where the consulting engineer's work comes in. The switchgear was supplied by a control technology firm and built by a third party panel integrator from bought out components. The cabinets arrived as flat pack units and were assembled on site. The report calls that on site assembly a critical point where a construction defect was introduced and never caught.

Nell Harding

Flat pack. I keep picturing wardrobes.

Theo Ashworth

It's not a bad picture, to be fair, as long as the wardrobe has a few thousand amps behind the doors. Think about the last time you built one and found a panel on upside down at the end. You can usually see it. Nobody dies. Here, nobody looked.

Nell Harding

What exactly did they find wrong?

Theo Ashworth

A list. Busbar to panel clearances differed on the two sides of the panel. Control and instrumentation cables were running directly over the busbars. Cable gland holes were not sealed. Loose hardware was resting on the busbars and inside the panels. And the headline defect: the partition cover of one vertical section was installed incorrectly, exposing the live busbar in the cable alley.

Nell Harding

Explain that one properly. What does installed incorrectly mean, physically?

Theo Ashworth

The internal wall inside the cabinet is meant to separate the cable alley, where people work on cables, from the busbars. The report says it should be fixed from bottom to top, leaving a gap at the top, not the bottom. It was fitted inverted, so the opening was in the wrong place, and the live busbars were exposed in the cable alley. It's a bit like fitting the guard on a saw the wrong way up, so the opening for the blade ends up where your hand goes. That's my analogy, not the report's, but the logic is the same. The thing that was supposed to keep you away from the live parts had been turned into the way to reach them.

Nell Harding

And the busbars themselves weren't protected either.

Theo Ashworth

No. The busbars and busbar droppers were bare, not sleeved, even though the specification required sleeving. The standard engaged is IEC 61439 part 1, clause 8.4.2.2. In substance, it requires hazardous live parts to be completely covered with insulation that can only be removed by destroying it, or by using a tool. The insulation has to be able to durably withstand the mechanical, electrical and thermal stresses it will see in service. The switchgear was found in a state not fully complying with that.

Nell Harding

So there are two layers there. Bare conductors, and then a partition that should have been a second line of defence, fitted so it wasn't.

Theo Ashworth

Plus a third. The doors were secured with hinges and latches. The report says access to bus compartments should require correct tools, and shields should be provided, and neither condition was met. Once the doors were opened, the panel reverted to what's called IP00, which means no protection against contact with live parts. So opening a latch took him from a closed cabinet to an open one with nothing in the way.

Nell Harding

Did the report look at whether the specification itself was weak?

Theo Ashworth

Only a little. Comparing the two switchgears in the same room indicated the specification was generic in nature. But the specification wasn't evaluated as part of the investigation, and the investigator expresses no opinion on its adequacy beyond noting that character. There's also one thing the engineer couldn't establish, which is the significance of metallic cable termination boxes in the cable alley. I like that the report says that rather than papering over it.

Nell Harding

There's a thread here that connects to the idea we keep coming back to in this series. The visible event is small. A man took a plate off and put it down. If you stop your investigation at that moment, you'd write down human error and go home.

Theo Ashworth

Which is the idea from the accident models episode, that the human act is where the investigation starts, not where it ends. Here the investigator makes it concrete. The panel was in a condition where a mundane slip could produce a fireball. That condition was built in before he was ever assigned the job. The question then becomes who should have noticed, and when.

Chapter 3

Nine Signatures and No Inspections

Nell Harding

Who should have noticed is the part I find hardest to get my head around, so let's do it carefully. Because there was supposed to be a system of inspection between a flat pack cabinet arriving and an engineer standing in front of it.

Theo Ashworth

There was, and the report counts about nine inspection hold points between construction and turnover. Let me read them out, because the length of the list is the point. A quality inspection of the cabinet construction by the Subcontractor. The same again by the EPC Contractor. The same again by the Project Management Team. Then a quality inspection of the installation of the electrical components. A pre energisation inspection. An energisation inspection. A pre commissioning inspection. A commissioning inspection. And a turnover package inspection.

Nell Harding

Nine chances.

Theo Ashworth

And the finding is that no quality checks were undertaken during construction. The EPC Contractor and the Project Management Team each signed off QA/QC acceptance with no inspection. The PMT quality manager said in interview that he rarely inspected physically and relied on information provided by the EPC Contractor. The turnover package manager admitted he never visited site, that his sign off was a desktop exercise, and that he generally read only the cover sheet before stamping. He subsequently resigned.

Nell Harding

Only the cover sheet. Let me push on this, because I can imagine someone saying that's one person being lazy. Is the report treating it that way?

Theo Ashworth

No, and I think that's the sharper reading. Look at how it's arranged. The PMT quality manager relied on the EPC Contractor's information. The EPC Contractor signed off without inspecting. The turnover manager relied on a package that had been signed off by the layers below. Each signature leaned on the one before it, and the first one in the chain was empty. It's like a row of people each checking the ticket of the person in front, and nobody ever looks at the train.

Nell Harding

And the report is clear about what an inspection would have done.

Theo Ashworth

It calls it a critical causal link. Had any one of the quality, pre energisation, energisation, commissioning or turnover inspections been carried out, the incorrectly constructed internal cabinet wall would have been identified early. And it goes further. A single working inspection at any of nine hold points would most likely have caught the defect that killed the engineer.

Nell Harding

That phrase, most likely, is doing honest work. It's not saying certainly.

Theo Ashworth

Right, it's a considered judgement. Now, the second paper control, the permit to work. The engineer's permit was obtained the day before. It was for mechanical works only. The activities specified did not state work on a live system, and the water treatment switchgear was nowhere mentioned. It wasn't a permit for the switchroom, and it wasn't a permit for electrical work.

Nell Harding

And the duration?

Theo Ashworth

The permit was dated for seven days, against an eight to twelve hour plan limit. So it was broad in time and narrow in scope, which is the wrong way round. And the investigator's conclusion is blunt. The work that led to the death was carried out without a valid permit to work for the activity actually undertaken. He also notes the deceased wasn't authorised to work on a live electrical system without a valid permit.

Nell Harding

Was anyone checking permits?

Theo Ashworth

No PTW audits were carried out by either the EPC Contractor or the Project Management Team. There was no task specific risk assessment for the activity that resulted in the death. The commissioning risk assessments were generic and effectively identical to the generic construction risk assessment. Method statements were poor, with essential information missing. Commissioning areas weren't adequately identified, and access control wasn't effectively managed. Then there's the key. An uncontrolled switchgear panel door key was held by the deceased, who wasn't authorised to hold it.

Nell Harding

So think about what he was walking through. The permit didn't mention the room. The key opened the door anyway. The risk assessment was a copy of a construction one. The inspections had been stamped. At every point where something could have said stop, the paper said carry on, or said nothing.

Theo Ashworth

That's close to how the investigator frames it. His method treats each of these as a barrier, a defence that should have arrested the sequence, and his finding is that every one had already failed before the engineer touched the panel. He doesn't say the engineer was blameless. He says the engineer arrived at the end of a chain where the failures had been accumulating without anyone noticing.

Nell Harding

And one more piece of timing. The work happened at lunchtime.

Theo Ashworth

It did. Work began around twelve, during the EPC lunch break, with no EPC supervision present. The report says that suggests the work proceeded without supervision by the principal EPC Contractor. And later, in the corrective actions, one of the recommendations is to prohibit work during the EPC lunch window, which tells you how the investigator reads that gap.

Chapter 4

Tools, Suits and a Culture

Nell Harding

Let's talk about what he had in his hands and on his body. Because the tool detail is the one I can't shake.

Theo Ashworth

The report calls a 240 volt line tester, a tester screwdriver, neither acceptable nor good practice in industry for this purpose. It says it provides no protection against the energy present in the switchgear. To be clear, the engineer wasn't being reckless with a better tool in the cupboard. The report describes it as the maximum rated tool available to him.

Nell Harding

So the site had no tool he could have used correctly.

Theo Ashworth

That's the implication, though I'd stay with the report's wording, which is that it was the maximum rated tool available to him. And the protective equipment tells the same story. The deceased wasn't wearing suitable PPE, and the general PPE was of poor quality and substandard. There was no evidence that the EPC Contractor or the Subcontractor held arc flash suits in their PPE stock. No evidence of insulating gloves in either party's stock. Rubber matting was present, but it didn't meet IEC and EN 61111, and it came from an unverified manufacturer.

Nell Harding

Matting that exists but doesn't meet the standard is oddly worse than no matting. It looks like protection.

Theo Ashworth

That's a good observation, and it's my reading too, though it's an interpretation. The same goes for the emergency response. The contributing factors list notes that only fire extinguishers were available at the scene. And it was the security guard at the door who used them. He wasn't a medic and wasn't part of the commissioning team. He was the person who happened to be there with an extinguisher.

Nell Harding

Now, on competence. The Subcontractor designated him for Demin plant commissioning across both instrumentation and electrical systems.

Theo Ashworth

Yes, and the review of his record showed work predominantly on PLC and instrumentation, with no suitable hands on electrical experience evident. There was no evidence he'd been trained on the panel concerned, or on the other panels he was made responsible for. The report's table of failures by accountable party puts it directly. The Subcontractor tasked an I&C engineer with electrical work he was neither trained nor authorised for. There was also no evidence of a toolbox talk by the Subcontractor, and the commissioning safety induction was poor, delivered by a safety officer with no commissioning safety experience.

Nell Harding

So who was meant to be watching all this? Where were the managers?

Theo Ashworth

This is the section that goes into what the investigator calls a pervasive production over safety culture and a pattern of absentee oversight. The PMT offices were about a hundred metres from the site. The team was described as complacent and not visible on site. A hundred metres. That's a short walk, the length of a football pitch, give or take.

Nell Harding

And the EPC safety people?

Theo Ashworth

The EPC HSE manager admitted visiting site only a few times per week, generally outside active periods, citing workload and language barriers between the workforce groups. The report says that language barrier left Subcontractors effectively unsupervised. And the EPC deputy HSE manager also served as deputy construction manager. The investigator calls that a conflict of role, and I'd put it plainly. The person who's supposed to be the check on the schedule is also the person responsible for delivering it.

Nell Harding

That one bothers me more than the absentee offices. Because absence is a lapse. A conflict of role is a design choice. Someone built that organisation chart.

Theo Ashworth

Fair point, and the report does list it among structural findings. There's also working time. Operatives routinely worked in excess of sixteen hours a day. I want to be careful here. The report says that about operatives generally. It doesn't say how long this particular engineer had been working that day or that week. So I wouldn't claim fatigue played a part in his decision. What I can say is that the project's pace was set so that long days were routine, and that's a sign of where the priorities sat.

Nell Harding

And the interviews with senior people.

Theo Ashworth

The investigator describes a complacent leadership tone from the top, and he gives two illustrations. First, one senior manager recounted that, as an apprentice, the practice had been to wet a finger and briefly touch a cable to check whether it was energised. The report notes the original statement was unusable for legal reasons, so this is offered as an illustration of the attitude he encountered. Second, a construction manager admitted he hadn't wanted to be on the project and rarely visited site.

Nell Harding

The wet finger story is almost a joke, until you remember what happened here. A man trying to find out if something is live, using a tool that can't tell him anything useful about the energy in front of him.

Theo Ashworth

I'd be careful about drawing a straight line, because the report doesn't. What it says is that such attitudes are indicative of the cultural conditions in which this fatality became possible. It's a statement about climate, not a claim about what any one person thought that day.

Chapter 5

Where the Blame Lands

Nell Harding

Let's get into how Dr Sundborg actually reasoned his way to a cause. He doesn't just list defects.

Theo Ashworth

He combines three methods. A bow tie sequencing of the event, a Five Whys drill down to root level, and a cross check against a fishbone analysis, the man, machine, method and management headings, so no causal branch was overlooked. The bow tie runs like this. The hazard is energised, unsleeved busbars exposed in the cable alley. The task is live fault finding with a 240 volt test screwdriver. The trigger is the metal cover plate slipping onto the exposed busbars. The event is a phase to phase arc flash. The outcome is burns to over ninety per cent of the body and death after ten days.

Nell Harding

And every barrier between those boxes was already gone.

Theo Ashworth

That's the claim. Now the Five Whys. Why did the engineer die? An arc flash engulfed him in flames, causing the burns and inhalation injury. Why did it occur? A metal cover plate slipped onto live exposed busbars. Why were they exposed and reachable? The partition was fitted incorrectly, the busbars were unsleeved, and he was doing live work with the doors open. Why was the defect never caught, and live work allowed? Nine inspections were signed off without inspection, and no valid electrical permit, risk assessment or supervision controlled the task. And the fifth why, why did the management system permit all that? A production over safety culture, with absentee oversight by the PMT and EPC teams and unenforced procedures. That's what he names the true root cause.

Nell Harding

Here's where I want to push, though. Whatever the culture, he still opened a live panel. He took the plate off. He made a choice. Isn't there a point where the individual owns that?

Theo Ashworth

The report doesn't dodge it. In the table of accountable parties, the individual is listed as having undertaken live fault finding without authority, valid permit, correct tools or PPE. The investigator calls the immediate unsafe act the deceased's. But he adds the qualifier that matters. Individual culpability is heavily mitigated. He was a young engineer, assigned a task outside his competence, without authority, supervision, correct tools or protective equipment, on a defective asset that should never have presented exposed live parts. The dominant failures lie with the management, quality and supply systems above him.

Nell Harding

I think that's right, and I'd like to say why in my own terms. Ask what a different person would have done. If you replaced him with another engineer from the same Subcontractor, with the same record, the same key, the same tool and the same instruction, the same panel would have been waiting. The unsafe act can be removed from the story and the hazard is still there.

Theo Ashworth

That's the heart of the thesis we've been working with through this series. Human error is the starting point of the investigation rather than the conclusion. The report states root cause in two parts. The unsafe condition was live busbars left exposed in the cable alley, with the internal partition fitted inverted and the busbars unsleeved, contrary to IEC 61439 part 1 clause 8.4.2.2. The unsafe act was live fault finding by an unauthorised, instrumentation biased engineer, under no permit for electrical work, with a 240 volt test screwdriver and no arc PPE. And then the line that links them. Why it reached him: nine QA/QC hold points signed off without inspection, no task risk assessment, no supervision, no lockout tagout control.

Nell Harding

The report also divides the failures by who was accountable.

Theo Ashworth

It does. The Project Management Team: absentee oversight, QA/QC and turnover packages signed as desktop exercises, no permit audits, a complacent leadership tone. The EPC Management Team: permit system not enforced, the HSE manager on site a few times a week, sub contractors effectively unsupervised, a production culture. The Subcontractor: incorrect panel build and installation, no toolbox talk, an I&C engineer tasked with electrical work. The Equipment Supplier: switchgear delivered not complying with IEC 61439 part 1, with unsleeved busbars, IP00 when open and no bus compartment shields. And last, the individual, enabled and directed by all the failures above.

Nell Harding

Five parties, and every one of them could have stopped it. That's what stays with me. It isn't one villain. It's a lot of reasonable looking gaps lining up.

Theo Ashworth

The contributing factors section says exactly that. Each factor removed or weakened a defence. No single factor caused the death; their accumulation did. And the conclusion goes on to say the arc flash was simply the moment at which those accumulated failures met a person.

Nell Harding

What does the report want done about it? This is the closing the loop part. An investigation that ends at blame isn't much use.

Theo Ashworth

The action plan is in three horizons, addressed jointly to the PMT, the EPC Management Team and the Subcontractor. In the first twenty four to seventy two hours: stop all live work, isolate the water treatment switchgear and apply lockout tagout, quarantine the panel and commission an independent arc flash hazard survey, suspend all permits and recall every uncontrolled key. The aim is to make the asset and the site safe.

Nell Harding

And then the repairs.

Theo Ashworth

Two to six weeks, owned by the Subcontractor and the EPC Contractor. Reissue the permit system and prohibit work during the EPC lunch window. Sleeve the busbars, refit the partition and verify the asset against IEC 61439 part 1. Re verify the competence of all commissioning personnel, and procure arc flash PPE and matting to IEC 61111. Then the systemic work, one to three months, with the Project Management Team in the lead. Re run all nine QA/QC hold points with genuine, witnessed inspection. Mandate a minimum PMT and EPC presence on site and institute a permit audit regime. Reset the commissioning safety culture and cap working hours.

Nell Harding

Notice who leads that last one. The people with the offices a hundred metres away.

Theo Ashworth

Yes. The people who stamped the cover sheet are the ones asked to repair the system that let them. I think that's deliberate. The report's closing statement says a single working control at any layer would most likely have prevented this fatality. A compliant panel, one genuine QA/QC inspection, a valid electrical permit, proper supervision, the correct tools, or arc rated PPE. And the duty now, in his words, is to ensure that no future task is allowed to proceed with every defence simultaneously down.

Nell Harding

Ten minutes, he said. It could have been a perfectly ordinary ten minutes, if any one of those things had been real. That's the line I'll carry out of this one.